| DATE | TASK | TEAM |
| Saturday 30/11/24 | Initial basic survey of Meteor and test cleaning carried out | Terry Tom |
| Saturday 7/12/24 | Start-up Meeting | Sam Tim Tom |
| Saturday 14/12/24 | Project Plan Creation | Tim |
| Sunday 15/12/24 | Radome condition analysis Fuselage sections cleaning | Terry Tom |
| 21-22/12/24 | Project Plan Approval | Sam Exec Committee |
| 28-29/12/24 | Order required equipment | Sam |
| Saturday 4/1/25 | PX24 test areas completed Canopy cover measurements | Tom Tim Terry Paul |
| 4-5/1/25 | Receive required equipment | Sam |
| Saturday 11/1/25 | Obtain canopy cover quote | Tim |
| Sunday 12/1/25 | Clean down airframe | ALL |
| Sunday 19/1/25 | Clean down airframe | ALL |
| Saturday 25/1/25 | Pitot probe repair and re-attach | Bill |
| Sunday 26/1/25 | Lubrication and PX24 application | ALL |
| Sunday 2/2/25 | PX24 application | ALL |
| Saturday 8/2/25 | Ready for Photoshoot | ALL |
| Sunday 16/2/25 | Canopy cover straps attach Cockpit clean | ALL |
| Sunday 23/2/25 | Landing light covers removal, dry, clean Cockpit clean | ALL |
| Sunday 2/3/25 | Radome re-paint Cockpit clean | ALL |
| Sunday 9/3/25 | Paint tribute markings | ALL |
| Sunday 16/3/25 | Paint tribute markings | ALL |
| Sunday 23/3/25 | Paint tribute markings | ALL |
| Sunday 30/3/25 | Reveal tribute markings | ALL |
| Sunday 6/4/25 | Ready for first Public Open Day | ALL |
-